Splitted peak integration in Chemstation - why?
Posted: Wed Jun 20, 2012 4:53 pm
Dear all,
we are trying to integrate a peak using an integration event with Chemstation and we have observed that the integration is not correct. The integration of the peak is splitted in two. Does anyone know why does it happen?

Should change/include any other parameter in the table?
We are using version A.09.xx.
Thanks a lot for your help!
we are trying to integrate a peak using an integration event with Chemstation and we have observed that the integration is not correct. The integration of the peak is splitted in two. Does anyone know why does it happen?
Should change/include any other parameter in the table?
We are using version A.09.xx.
Thanks a lot for your help!