We plan to move laboratory instruments to new QC building (HPLC/UPLC, GC and other). Is it necessary to perform complete IQ/OQ/PQ after the moving to the new lab. If it is not necessary, is it enough to perform some functionality test (repeating of the last analyses on the same systems after the moving is done).
1. In our case, some of the instruments will be requalified immediately after moving since the regular qualification interval is close to the date of moving.
2. Some of the equipment will be qualified couple of months before moving to the new lab-the question is – Is it enough to have only IQ after the moving is done or it is necessary to perform IQ /OQ and PQ again?
3. Some of the equipment has the regular qualification date 6 months after the moving date– Is it enough to have only IQ after the moving is done and then to wait the date of regular qualification?
Thank you all